Steel block fabrication and blasting-painting works on Hydra under Norse Group.

CMS AS took end-to-end responsibility for steel production and outfitting on the NB14 - Hydra Steel Block Fabrication project at NORSE GROUP. With a modern machine park and a qualified workforce, CMS AS sustained the required quality even under tight schedule pressure. The balance of time, cost and quality was observed at every stage of the project.

Scope of Work

Services provided by CMS AS throughout the project:

  • Block Fabrication: Fabrication of ship blocks through CNC cutting and forming of steel plate and panel-line assembly.
  • Surface & Coating: Surface preparation (abrasive blasting) and protective coating for corrosion protection.
  • Steel Fabrication: Industrial steel-structure fabrication, machining and welded assembly.

Engineering & Execution

Traceable material management, in-process inspections and final-control steps kept production under control from start to finish, with non-conformities resolved quickly on site. Transitions between work items were planned with site safety and efficiency in mind. Material certificates, welding records and inspection reports were fully documented to preserve complete traceability.

Standards & Quality Assurance

Production was completed in full compliance with international maritime and industrial standards. Welding was performed to WPS/WPQR-approved procedures and verified by NDT (UT/RT and visual inspection). Surface preparation was to ISO 8501-1 (Sa 2½) cleanliness and the protective coating applied to an ISO 12944 system.

As a result, a robust steel structure that will add value for years was delivered. The project was thus completed in line with budget and schedule targets. The experience CMS AS has accumulated in shipbuilding and industrial steel since 1990 makes it a trusted solution partner for shipyards.

Build Journey

Production stages CMS AS undertook on this project

  1. Design & Engineering

    Delivered by CMS AS

    Production drawings, cutting plans and work preparation

  2. Steel Cutting & Block Fabrication

    Delivered by CMS AS

    CNC cutting, forming and panel-line fabrication

  3. Erection & Assembly

    Joining and welding of blocks on site

  4. Piping & Outfitting

    Piping circuits, HVAC and equipment installation

  5. Surface Prep & Coating

    Delivered by CMS AS

    Blasting (ISO 8501-1) and protective coating (ISO 12944)

  6. Testing & Delivery

    Delivered by CMS AS

    Inspection, testing and handover

Canlı AIS Konumu — IMO 9887530

Canlı konum için MarineTraffic →

Project Gallery

IMO Doğrulanmış
IMO 9887530
Hydra
MarineTraffic'te Takip Et

Project Details

Category
Steel Fabrication
Üst Yüklenici
NORSE GROUP
Gemi / Müşteri
Hydra

İş Kapsamı

ÇELİK BLOK İMALATI
KUMLAMA & RASPA BOYA

Looking for a Similar Project?

Our expert team is ready to evaluate your needs.

Contact Us